We provide you with hassle-free, innovative solution ecosystems for strategic logistics management, warehousing and transportation

Working Hours

Case Studies

Client Specific Case Studies

ACC Cement

Challenge
The ACC CEMENT company began operations in Pune in 1986. Initially, there was limited track space for only 6 railway wagons, causing delays in unloading due to space constraints, thus hindering sales growth.
Solution
Raghoji group negotiated with the railways to construct an extension of tracks capable of accommodating 20 wagons exclusively for the customer.
Impact
The unloading time was reduced drastically thus empowering their distribution process. The company was able to use the extension facility exclusively for 9 years. The last-mile connectivity helped them optimize time and cost and built brand credibility.

Jaypee Group

Challenge
Jaypee Group sought to expand into Maharashtra and was searching for a trustworthy partner to provide them with logistic operations post unloading from the railways. They also needed a product distribution system for smaller deliveries.
Solution
Raghoji Logixs provided material handling services with absolute stock accuracy. We established an extensive distribution network with deep-pocket deliveries.
Impact
Our operational experience helped the industry increase its sales. Our brand-strengthening efforts in the targeted region helped the company tap into newer markets.

Tata Toyo Radiators

Challenge
  • Recurring Packaging Cost of WDN Box
  • Product Damage Probabilities
  • Waste of Natural resources
  • Heavy CAPEX investment in Steel Pkg of Metal Skid.
Solution
  • Use of reusable metal Skid
  • Robust design with engineering approach to protect any handling, Transit damage.
  • Optimization of Supply chain cost by establishing forward & reverse logistics SETUP.
  • Automation of Skid accounting System
  • CAPEX Investment by Supplier with ownership of complete Supply Chain & Logistics
Impact
  • AVG .20 % Cost saving of overall Wooden Packaging Cost & allied Supply chain areas, i.e. Damage, Warehousing, Transportation.
  • 100% outsourcing with Single Point Ownership by Supplier of Metal Skids & Complete Logistic Process of Skid Packaging.

Service Specific Case Studies

Warehousing & Supply Chain Management

Challenge
One of our top automobile tyre customers in Pune had to replace their logistics partner suddenly. They required the complete supply chain setup to be completed within a month and sought a service provider capable of maintaining operations without any decrease in service quality.
Solution
Raghoji group embraced the challenge. We selected a warehouse site, established a warehouse per the client’s requirements, improved the current workforce, and reorganized backend procedures to initiate supply chain operations within the agreed timeframe. We delivered services complying with the existing standards, ensuring no labor disturbance.
Impact
The transition happened smoothly without any loss of sales. The company could scale their operations with a 50% increase compared to previous years.

Stock Accuracy & FIFO Optimization

Challenge
For one of our top tyre customers, a fixed location catering to product specifications was not maintained. A disrupted FIFO system resulted in problems like misplacement of Tyres, underutilization of available space, extended picking times and poor stock accuracy.
Solution
For one of our top tyre customers, a fixed location catering to product specifications was not maintained. A disrupted FIFO system resulted in problems like misplacement of tyres, underutilization of available space, extended picking times and poor stock accuracy.
Impact
The stock accuracy increased from 90 to 100%. FIFO was properly maintained. The average picking and loading time decreased from 3 hours to 2 hours.

Technological
Integration

Challenge
At one of our client sites, we encountered challenges handling goods. A diverse range of products were stored in the warehouse. The demand and supply were unpredictable. The stock records and FIFO processes were reliant on the client’s system causing delays in issuing material.
Solution
We have begun developing a computer-based warehouse software, customized to meet the demands of the business. It provides solutions to reduce FIFO manual dependency, improve accuracy and manage real-time stock situations.
Impact
The software implementation is saving us time, as we can now track individual stocks and maintain stock quantity records efficiently. This has greatly enhanced stock accuracy, thus reducing the dependency on manual intervention.

OUR CLIENTS FEEDBACK

Testimonials